          India's bullet train project faces land acquisition hurdles
          Source: Xinhua   2018-06-02 16:25:57

          NEW DELHI, June 2 (Xinhua) -- India's Mumbai-Ahmedabad bullet train project has hit a land acquisition hurdle as locals are refusing to give their land for the ambitious plan, local newspaper Economic Times reported Saturday.

          The resistance is being shown by villagers from local communities and tribals in Palghar district of Maharashtra.

          "More than 70 tribal villages of Palghar district in Maharashtra have refused to give land for the project and an agitation is building up against the proposed rail corridor that will pass through these villages," the newspaper report said.

          The construction for India's first high-speed train project, the 508 km long train corridor, was to begin in January 2019 and the deadline for land acquisition was the end of this year.

          The 110 km of the corridor is passing through Palghar district.

          The 14.6 billion-U.S. dollar project connecting the capitals of Maharashtra and Gujarat is expected to be constructed by August 2022.

          Authorities however are hopeful to resolve the stand-off and begin the work on scheduled time.

          "We are facing resistance in some parts of Maharashtra but are hopeful that the construction of the project will begin as per our timeline. We are offering five times the circle rate of land as compensation to people whose land is being acquired," the newspaper quoting a railway ministry official said.

          Indian Railways is acquiring around 1,400 hectares of land for the project.

          The Indian government has already started getting funds from the Japanese International Cooperation Agency (JICA) and the land acquisition has begun in some parts of Mumbai.?

          Editor: Shi Yinglun
          Related News
          Xinhuanet

          India's bullet train project faces land acquisition hurdles

          Source: Xinhua 2018-06-02 16:25:57
          [Editor: huaxia]

          NEW DELHI, June 2 (Xinhua) -- India's Mumbai-Ahmedabad bullet train project has hit a land acquisition hurdle as locals are refusing to give their land for the ambitious plan, local newspaper Economic Times reported Saturday.

          The resistance is being shown by villagers from local communities and tribals in Palghar district of Maharashtra.

          "More than 70 tribal villages of Palghar district in Maharashtra have refused to give land for the project and an agitation is building up against the proposed rail corridor that will pass through these villages," the newspaper report said.

          The construction for India's first high-speed train project, the 508 km long train corridor, was to begin in January 2019 and the deadline for land acquisition was the end of this year.

          The 110 km of the corridor is passing through Palghar district.

          The 14.6 billion-U.S. dollar project connecting the capitals of Maharashtra and Gujarat is expected to be constructed by August 2022.

          Authorities however are hopeful to resolve the stand-off and begin the work on scheduled time.

          "We are facing resistance in some parts of Maharashtra but are hopeful that the construction of the project will begin as per our timeline. We are offering five times the circle rate of land as compensation to people whose land is being acquired," the newspaper quoting a railway ministry official said.

          Indian Railways is acquiring around 1,400 hectares of land for the project.

          The Indian government has already started getting funds from the Japanese International Cooperation Agency (JICA) and the land acquisition has begun in some parts of Mumbai.?

          [Editor: huaxia]
          010020070750000000000000011100001372253421
          无码人妻一区二区三区四区av_亚洲精品911在线永久观看_精品一区二区国产在线观看_日韩不卡一区二区视频在线

                  天天看片高清观看免费国产 | 中文亚洲成a人片在线播放 亚洲AV乱码久久精品蜜桃 | 亚洲中文字幕丝祙制服在线 | 亚洲国内精品自在自线国产精品 | 亚洲午夜成年在线网站 | 午夜理论欧美理论片久久 |